This is Our Livening Process It Includes Safety Checks, Test Results & Temp Supply Decoms
    Safe Working
    Emergency Planning

    Job sites vary from day to day so it is important to establish a plan in the event there is an accident.

    C
    onsider your own safety first
    Decide on a safe plan
    Always stay calm
    Establish an Assembly Location

    Injury procedures

    Shut down plant or equipment
    Take safe actions to control event
    Prevent further harm or damage
    Provide first aid
    Stay with Injured
    Dial 111 and ask for AMBULANCE

    Fire
    Evacuate the site to the safe area
    If safe to do so extinguish the fire
    Dial 111 and ask for FIRE

    Earthquake procedures
    Keep clear of structures
    Evacuate the site to the safe area

    Remain in the assembly area
    ​

    Gas Leak
    Evacuate the site to the safe area
    Stay upwind of the leak
    If safe eliminate the leak
    Dial 111 and ask for FIRE
    Livening the Connection After Livening take Photos off the metering switchboard & Orion box
    The Test Results
    First Read is the voltage
    Second Read is Insulation Resistance in Mega Ohms
    Third Read is Loop Line in ohms 
    Example 230 - 999 - 0.49
    RCD Test Results 
    First Read in ms at 30mA
    Second Read in ms at 150mA
    Third Read is Ramp in mA
    Forth Read is 1/2 Rated (no trip)
    ​E
    xample 27 - 9 - 25 - no trip
    Decom Builders Temp Supply (BTS) 
    ​
    You Must get a photo of the meter reads before disconnecting
    Tested by Brendan Yates Practicing Licence Number I3012